Friday, 43rd day of the build

Sparky and his helper were here this morning. They ran the conduits to the second level and outside fixture for the deck.

Block has reach 12 ft on the front section. Working on add rebar to second level and to the 16th ft level on the over the auto lift should be finished this afternoon.
Masons are coming Saturday to finish to the rest of the walls .. and will have grout poured in Monday and inspection. They can then finish to the 18ft level on Tuesday





Framing plan to start the 18th

Dust Nazi wanted the hose moved to cover more of the lot.

Pics later this afternoon

The house inspector showed up this morning .. happy and all smiles


End of day pics





__________________
BMWMOA 82741 ABC 8418
2wheeltraditions@gmail.com
75 R90S , 88 R100GS ,94 R1100RS (Aragorn) 2k 1150GS DMC sidecar,
R nine T

walkingbear screwed with this post 06-11-2012 at 06:38 PM
walkingbear is offline   Reply With Quote