Friday and the trusses are up

Pretty hot here today.

110 at noon, 5 guys with hammers and one crane operator.

The trusses are up, beams are up, some of the plywood roof are nailed down.
A few changes has to be made in front. The 3 little windows won't fit so we are going with sky lights on the eastern side. We will make changes as we work.

We now have a steps to the upper level. Totally different from last week.
Last 30 days of construction (we hope). We will be totally under roof by Tuesday afternoon.
Electricians are happy that we have finished this part. Now they can run their lines.

Tile installer came out and remeasured the bathroom. Added a 2x4 window in the bath area.





















Clearing out motar so the beam would fit












These guys trust each other. Something that big floating around held by two straps























__________________
BMWMOA 82741 ABC 8418
2wheeltraditions@gmail.com
75 R90S , 77 R100 RS,88 R100GS ,94 R1100RS (Aragorn) 2k 1150GS DMC sidecar,
R nine T

walkingbear screwed with this post 06-30-2012 at 09:39 PM Reason: adding info
walkingbear is offline   Reply With Quote