A few things we are doing and waiting for:
Civil engineers were out to take final height measurement. To make sure we we didn't exceed out 23 roof line height. ( they out here for 30 mins and charged $850 to measure the corners, ceiling and roof line)
Insulation bid for fiberglass batts.Plan#: Trade: INSULATION
Work Area Product Notes
R 30 WITH SCRIM R-30 UNFACED BATT INSULATION WIRED TO DECK
R 19 BATTS GABLE WALL R-19 UNFACED BATT INSULATION STRAP IN BATTS
R 19 SCRIM ATTIC WALL R-19 UNFACED BATT INSULATION
OVER BATTS FSK HD FACING 54"
Base Price: $1,329.00
Additional Information: BASE INSTALL: $1329
ADD OPTION: + $115
PLS INITIAL IF SELECTED
TAX IF APPLICABLE: 5.82%
HVAC contractor on running duct work and heat pump unit
( est this evening $5600 with duct work plus 3 ton unit big enough for expansion )
Re-config the upstair windows (made them 8 inch smaller ) the drywall was going to be too close and the door wouldn't fit. instead of 6'x4 opening it will be 5'4 x4. Small price to pay rather than re-framing.
While we were away they re-framed the pony wall to the stairway to 4 feet to keep the kids being able to reach and climb the shorter wall.
Black tar water proofing will start Tuesday.
Waiting for others to come by .. more later
It is amazing how things get backed order. Shower pan is 10 business days
Swanstone 54"L x 34"W White Shower Floor
Item #: 170866 | Model #: FF03454MD.010
A couple of $100 here and there and we are still not close to being finished. The roofing tiles will be delivered this week and we will have to wait 3 weeks for the tile to settle the house before the tiles are set. Dry wall will not start until the roof is finish. Something about weight load on the room will keep drywall from cracking.