saturday morning.. final day concrete, tree deck is going up

Lots of people are here this morning. My carpenter and his helper, the concrete guys pouring the ribbon and me .. making the coffee and running to Lowes for extra material.

First the tree house is taking form. The deck is up and we came up a different framing plan for the crows nest,

The deck is fully covered. We are going to add an additional platform .. 5 feet from the deck



framing and the composite decking




we are adding an additional block under the joist hangers. We wanted take addition strength to the hanger.


headers are 4x8 x12 joist are 4 x 6 x 8










Friday we worked on the landscaping water control. We have water control piping under the concrete driveway.




__________________
BMWMOA 82741 ABC 8418
2wheeltraditions@gmail.com
75 R90S , 77 R100 RS,88 R100GS ,94 R1100RS (Aragorn) 2k 1150GS DMC sidecar,
R nine T

walkingbear screwed with this post 01-09-2013 at 10:48 AM
walkingbear is offline   Reply With Quote